Denton, Denton County, TX · ERCOT
$1.2B expansion adding ~70MW at Denton site (Feb 2025), part of ~590MW total CoreWeave contracted across six Core Scientific sites totaling $10.2B over 12-year terms. CoreWeave agreed to acquire Core Scientific (~$9B all-stock) July 2025.
The essential facts on record for this project and how confident we are in them.
Site imagery and location context.
No imagery on record yet.
Every organization and person with a known role in this project, with the evidence behind each relationship.
| Role | Party | Assertion | Confidence | Start | End |
|---|---|---|---|---|---|
| developer | Core Scientific, Inc. | reported | low | Unknown | current |
| tenant | CoreWeave | reported | low | Unknown | current |
How big this project is, by each distinct measure. These figures measure different things and are never added together.
| Type | Kind | Scope | Value | As of | Assertion | Confidence |
|---|---|---|---|---|---|---|
| announced campus | actual | Campus | 70 MW |
The project's path to utility power: interconnection requests, approvals, and delivery infrastructure.
Power generated on site without going through the utility grid.
Gas supply arrangements feeding on-site generation.
Where the project's water comes from and how the facilities are cooled.
Network connectivity: routes, carriers, and diversity.
The land under the project and how far the site could ultimately grow.
Who is building the project and the major equipment on order.
What the project costs, how it is financed, and the commercial agreements behind it.
Permits, zoning, tax arrangements, and public incentives.
Every dated event on record, newest first. Superseded entries stay visible.
What changed in this record recently, and why.
| Date | Field | Change | Cause |
|---|---|---|---|
| 2026-07-15 | generalized centroid | (empty)->{"lat":33.217449,"lng":-97.141346,"accuracy":"city","geoc... | geocode |
| 2026-07-15 | capacity rollup | {"rollup":{},"headlineMw":null}->{"basis":"announced_campus","rollup":{"announced_campus":... | system rollup |
| 2026-07-15 | executive summary | (empty)->$1.2B expansion adding ~70MW at Denton site (Feb 2025), p... | claim accepted |
Our readiness assessment across thirteen dimensions, plus known risk notes and open questions.
| Dimension | Rating | Conf | Evidence summary | Open questions | Blocking issues | Last verified |
|---|---|---|---|---|---|---|
| Land control | Unknown | unknown | Unknown | Unknown | Unknown | Unknown |
| Contiguous land | Unknown | unknown | Unknown |
Every source cited by the accepted facts in this dossier.
| Title | Publisher | Tier | Type | Published | Retrieved |
|---|---|---|---|---|---|
| Denton, TX HPC Site Expansion - investors.corescientific.com | investors.corescientific.com | T3 | news article | Unknown | 2026-07-12 |
| Unknown |
| reported |
| low |
| Unknown |
| Unknown |
| Grid path | Unknown | unknown | Unknown | Unknown | Unknown | Unknown |
| BTM readiness | Unknown | unknown | Unknown | Unknown | Unknown | Unknown |
| Fuel supply | Unknown | unknown | Unknown | Unknown | Unknown | Unknown |
| Water | Unknown | unknown | Unknown | Unknown | Unknown | Unknown |
| Fiber | Unknown | unknown | Unknown | Unknown | Unknown | Unknown |
| Permitting | Unknown | unknown | Unknown | Unknown | Unknown | Unknown |
| Equipment | Unknown | unknown | Unknown | Unknown | Unknown | Unknown |
| Financing | Unknown | unknown | Unknown | Unknown | Unknown | Unknown |
| Offtake | Unknown | unknown | Unknown | Unknown | Unknown | Unknown |
| Construction | Unknown | unknown | Unknown | Unknown | Unknown | Unknown |
| Community & political | Unknown | unknown | Unknown | Unknown | Unknown | Unknown |