Grid interconnection positions and behind-the-meter generation. Grid and BTM are always modeled separately; one never implies the other.
Requested MW is a queue position, not an approval; approved MW appears only when a study or interconnection agreement grants it.
BTM role (bridge / permanent / backup / hybrid) is recorded explicitly; BTM capacity never implies a grid connection exists or is replaced.