state - US-TX
Implements SB 6's mandate that the PUCT create interconnection standards for new loads of 75 MW or greater in ERCOT. The draft published March 12, 2026 contemplates site control demonstrations, financial security, interconnection fees, and disclosure of similar interconnection requests by the same entity or affiliates, aimed at mitigating stranded transmission risk and improving system planning. Comments were due April 17, 2026.
ERCOT region (Texas)
Watch for adoption timing and final financial-security levels; affects every ERCOT large-load queue position including Batch 1 filings.